ESP components · Gas flow conditioning
Gas distribution screens for electrostatic precipitators
A gas distribution screen ESP retrofit or new-build package uses perforated plates of 40–60 % open area, with splitter and turning vanes in the inlet nozzle, to spread flue gas evenly across the fields. The target is ICAC EP-7 uniformity — velocity standard deviation σ ≤ 15 % of mean — because the Deutsch equation punishes maldistribution exponentially.
01 — Function
Why velocity uniformity is a first-order design variable
The precipitator's electrical system can only collect the gas that passes through it slowly enough.
Flue gas reaches the precipitator through a duct perhaps a tenth of the area of the ESP face, expands through an inlet nozzle, and must then travel through the fields at a low, even velocity. Left alone it will not: the jet from the duct drives a fast core through the middle of the casing while the corners recirculate. Gas distribution screens — perforated plates across the inlet face, fed by splitter and turning vanes in the nozzle — impose the even profile that every other part of the electrostatic precipitator design assumes. The industry acceptance criterion is ICAC standard EP-7: standard deviation of velocity σ ≤ 15 % of mean, measured by traverse across the treatment cross-section.
Uniformity is not cosmetic. The specific collecting area of the design-basis ESP, 75.7 s/m on 3,888 m² of plate, is a statement about residence time; a fast path through the casing is locally an undersized precipitator. Maldistribution also drives secondary damage: high-velocity zones scour collected dust off the collecting electrodes and re-entrain it, while dead zones drop ash in the inlet nozzle and on the screen itself. On bagasse and rice-husk duty the fly ash is high in abrasive silica, so a fast corner also erodes plates and vanes years ahead of schedule.
02 — The arithmetic
The exponential penalty
Deutsch-Anderson makes the cost of maldistribution calculable — and it is worse than intuition says.
Why does uneven gas flow cut ESP efficiency so sharply?
Because collection follows η = 1 − exp(−w·A/Q), penetration rises exponentially where gas moves fast. A zone running 30 % above mean velocity does not leak 30 % more dust — it can leak roughly double. Averaging fast and slow zones never cancels out, because the fast zone's excess always outweighs the slow zone's gain.
Take the design-basis four-field ESP: 96.67 % collection on the 720 mg/Nm³ leaving the Electrocyclone, hence exp(−w·A/Q) = 0.0333 and w·A/Q = 3.40 at uniform flow, for an outlet of 24 mg/Nm³. Now split the same total flow so half the face runs 30 % fast and half 30 % slow. The fast half sees w·A/Q = 3.40/1.3 = 2.62, penetration 7.3 %; the slow half 3.40/0.7 = 4.86, penetration 0.8 %. Flow-weighted penetration is about 4.0 % — the outlet rises to roughly 29 mg/Nm³ with not one bolt changed inside the casing. Real precipitators on polydisperse dust follow the flatter Matts-Öhnfeldt form (k ≈ 0.5), which softens the numbers but not the conclusion: the fast zones set the stack reading.
This is also why a controller upgrade cannot substitute for flow correction. The ESP controllers hold each field at the highest voltage the gap allows, but voltage acts on migration velocity w, and no achievable increase in w buys back a 30 % local deficit in residence time. Screens first, electronics second.
03 — Hardware
Screen selection: open area, vanes, materials
Coarse correction in the nozzle, fine correction at the face.
Distribution is staged. Splitter and turning vanes in the inlet nozzle take the duct jet and spread it through the expansion, doing the coarse work; one to three perforated screens at the ESP face then flatten what remains. Plate open area is the key selection, chosen in the 40–60 % range: lower open area corrects harder but costs pressure drop — which the ID fan pays for continuously — and blinds faster on sticky ash. Where dust drops out in the nozzle, the screen package includes hopper baffles so the inlet hopper is not short-circuited by sneak-by flow beneath the fields.
| Element | Position | Open area | Material | Key dimensions |
|---|---|---|---|---|
| Perforated screen, first | ESP inlet face | 40–50 % | Carbon steel; stainless option for sticky or corrosive ash | CONFIRM: Arrow standard plate thickness and hole diameter |
| Perforated screen, second | Downstream of first screen | 50–60 % | Carbon steel | Panel sizes set by manway access; CONFIRM: standard panel module dimensions |
| Splitter / turning vanes | Inlet nozzle | — | Carbon steel; wear liners on high-silica ash | Chord and pitch set by CFD per nozzle geometry |
| Outlet screen (where fitted) | ESP outlet face | 50–60 % | Carbon steel | Suppresses outlet-nozzle swirl and sneak-by |
| Screen rappers | First screen, sticky-ash duties | — | As rapping systems | Sequenced with field rapping |
CFD versus physical flow model. CFD on the full duct-nozzle-casing geometry is the standard design route: it is fast, iterates cheaply, and resolves the vane geometry directly. A reduced-scale physical flow model still earns its cost where the inlet arrangement is unusual — twin inlets, tight duct bends hard against the nozzle — because it measures rather than predicts. Arrow treats neither as acceptance: the contract criterion is the site velocity traverse at the inlet face, σ ≤ 15 % of mean, witnessed before the internals go live.
04 — Service behaviour
Fouling, failure modes and symptoms
A distribution screen fails quietly — the symptom appears at the stack, not on a panel.
How do you know a gas distribution screen has fouled?
The electrical readings stay normal while outlet dust climbs. Blinded holes force the remaining flow through a smaller area, so local velocity rises and the exponential Deutsch penalty does the rest. A traverse, or simply an outage inspection of the first screen, separates screen fouling from resistivity or electrode problems that mimic it.
Bagasse firing makes fouling a design case, not a rarity: fuel at roughly 50 % moisture gives a wet gas, and unburned char is soft and adhesive. On such duties the first screen carries its own rappers, sequenced with the field rapping.
- Blinded screen panels (sticky ash, condensation during start-up)
- Rising outlet dust at unchanged kV/mA; ash ledge visible on the screen at inspection. Fit or repair screen rappers; review start-up heater practice.
- Broken panel fixings, panels vibrating or fallen
- Sudden loss of distribution; step change in opacity. Check fixings at every outage — a fallen panel can also short the inlet field.
- Vane and screen erosion on high-silica ash
- Holes wear oval, correction weakens gradually over years. Wear liners on vanes; thickness checks at major outages.
- Corrosion at cold corners and around casing inleakage
- Localised plate loss near doors and penetrations. Fix the inleakage first, then the steel.
05 — Retrofit
Retrofit procedure, replacement and interchangeability
Screens are the highest-leverage mechanical retrofit inside an existing casing.
A retrofit runs in five steps. First, a diagnostic velocity traverse of the existing precipitator, plus inspection of nozzle and screens, during a short outage. Second, CFD of the as-found geometry, calibrated against the traverse. Third, design of the correction package — vanes, screen open areas, baffles — iterated in the model until predicted σ ≤ 15 % of mean. Fourth, fabrication as bolt-in panels sized to pass through existing manways, so no casing cutting is needed. Fifth, installation in a planned outage and a verification traverse before hand-over. Guaranteed performance figures are stated per project after this assessment, on a stated basis (mg/Nm³, reference O₂, dry/wet, load range).
Arrow Energy Co., Ltd. supplies distribution screens and vane packages as internals for other OEMs' casings, not only its own. The compatibility question is purely dimensional — face dimensions, nozzle geometry, manway sizes, existing support steel — so every third-party retrofit begins with a dimensional survey of the casing, from which panels are detailed to suit. Where the survey shows the real problem lies elsewhere, Arrow says so: a precipitator with good distribution and poor plates needs collecting electrodes, not screens.
FAQ
Engineering questions, answered
What gas velocity uniformity should an ESP have?
The accepted criterion is ICAC standard EP-7: the standard deviation of gas velocity across the treatment cross-section should not exceed 15 % of the mean velocity, verified by a point-by-point traverse at the inlet face. Precipitators failing this criterion give up outlet performance no amount of electrical tuning recovers.
How much ESP efficiency is lost to poor gas distribution?
Because collection follows the exponential Deutsch relation, fast zones leak disproportionately. On the design basis — 96.67 % ESP collection, 720 mg/Nm³ inlet — a split with half the gas 30 % fast and half 30 % slow lifts the outlet from 24 to roughly 29 mg/Nm³ at 6 % O₂ dry, with unchanged total flow and collecting area.
What open area should ESP distribution plates have?
Perforated distribution plates are selected in the 40–60 % open-area range. Lower open area gives stronger flow correction but higher pressure drop and faster fouling on sticky ash; higher open area does the reverse. Screens are usually staged, with the coarser correction done by splitter and turning vanes in the inlet nozzle.
Is CFD enough to design gas distribution, or is a physical model needed?
CFD resolves the full duct-and-nozzle geometry cheaply and is the normal design tool. A physical flow model remains worthwhile for unusual inlet arrangements or litigation-proof verification, since it measures rather than predicts. Either way, acceptance is the site traverse: measured σ ≤ 15 % of mean velocity at the inlet face.
Do gas distribution screens foul on sticky ash?
Yes. High-moisture flue gas — bagasse firing runs on fuel at about 50 % moisture — and fine char can blind screen holes, locally accelerating the remaining flow. Fouled screens show as rising outlet dust at unchanged electrical readings. Screens on such duties get dedicated rappers and are inspected at every outage.
Related engineering pages
Send us your plant data
Fuel, boiler capacity, gas flow, current emission and the limit you must meet. An Arrow engineer replies with a technical assessment basis — not a brochure.