Services · Cold & hot commissioning

ESP and boiler commissioning: from air-load curves to the guarantee test

ESP commissioning proves a precipitator field by field before dust ever enters it: alignment checks, insulator megger, rapping function, then air-load V-I curves — corona onset through to controlled sparkover — followed by gas-load tuning and a performance test in mg/Nm³ at a stated O₂ reference per EPA Method 5 or ISO 9096.

Stable corona to controlled sparkover, per field (indicative onset 15–25 kV)
Air-load V-I acceptance
> 1 GΩ at 5 kV DC
Support insulator megger (indicative)
mg/Nm³ @ stated O₂, dry
Guarantee-test dust basis
EPA Method 5 / ISO 9096
Isokinetic traverse standard

01 — Why commissioning is a sequence

ESP commissioning: prove each layer before loading the next

Mechanical truth, then electrical health, then gas, then dust, then the guarantee test.

A precipitator that starts badly rarely recovers by tuning. If plates are 8 mm out of alignment in a 300 mm duct, the first field will spark early for the rest of its life; if an insulator tracks on day one, the fault current will be blamed on everything except the insulator; if the guarantee test runs without an agreed O₂ reference, the number it produces is unusable by either party. Commissioning exists to catch each of these at the layer where it is cheap to fix — which is why Arrow Energy Co., Ltd. commissions in a fixed sequence within our boiler and emission-control services scope: cold checks with the casing open, electrical proving on ambient air, hot tuning on gas, and only then the performance test.

The same discipline applies whether we commission our own supply — a new electrostatic precipitator, a rebuild delivered under an ESP upgrade, or a complete train — or act as commissioning engineers for equipment supplied by others. The record produced in the first week becomes the plant's electrical and mechanical baseline for the next twenty years.

02 — Cold commissioning

Cold commissioning: alignment, insulation, rapping, air-load V-I

Everything that can be proven without flue gas is proven without flue gas.

With the casing open and locked out, discharge and collecting electrodes are checked against design clearances — an alignment error of a few millimetres on a nominal 300–400 mm duct costs sparkover voltage directly, since the field can only be raised as high as its worst clearance allows. Rappers are stroked through full travel, drop hammers and drive shafts checked for free movement, hopper heaters, level switches and purge air verified. Gas distribution screens are inspected against the model or drawing.

Closed up, the electrical layer is proven. Support and shaft insulators are meggered — indicatively above 1 GΩ at 5 kV DC after heater soak — because a damp or tracking insulator is the most common single cause of a field that will not hold voltage. Interlocks, key exchange and earthing are function-tested before the first energisation.

Then each field is energised on ambient air and its V-I curve recorded. A healthy air-load curve is unmistakable: essentially zero current until corona onset — indicatively 15–25 kV depending on discharge electrode geometry — then a smooth, steep, monotonic rise of current with voltage up to a clean, controlled sparkover. Three deviations tell three stories. Sparking well below the expected ceiling means a clearance or a foreign object. A curve shifted right with depressed current suggests insulator leakage or a wiring fault. Identical fields producing visibly different curves mean asymmetry — alignment, dust ledges from a previous life, or a damaged electrode. Every one of these is cheaper to fix now than under gas. The air-load curves are archived: years later, comparing a suspect field against its commissioning curve is the fastest diagnostic the plant owns.

03 — Hot commissioning & boiler side

Gas-load tuning — and the boiler work that must precede it

The precipitator is commissioned on the gas the boiler actually makes.

Hot commissioning starts only when the boiler delivers stable gas within the precipitator's design window — for bagasse duty typically 150–180 °C at the ESP inlet, never above the 200 °C service limit — because tuning against a swinging inlet condition produces settings that are wrong at every steady state. Under flue gas, the curves change character: space charge from dust raises the voltage the field can hold, and the working point moves. Gas-load V-I curves are recorded per field and compared with air-load; the automatic voltage controllers are then tuned — spark rate setpoints, quench and ramp recovery, intermittent energisation where resistivity demands it — field by field, from inlet to outlet. Opacity is correlated against load and soot-blowing so the plant can later distinguish a real emission change from an operating artefact. Rapping is optimised last, against the opacity trace: intensity and interval per field, slower toward the outlet where re-entrained dust has no downstream field to catch it.

On combined boiler-and-ESP projects, the boiler side is commissioned in parallel and in its own strict order: refractory dry-out on a controlled temperature ramp — indicatively 25–50 °C/h with soak holds per the refractory schedule — so trapped water leaves as vapour rather than as spalled brickwork; safety-valve floating and set-pressure verification; steam-line blowing repeated until target-plate cleanliness acceptance criteria (agreed per project against the turbine or process requirement) are met; and water-chemistry passivation runs to establish the protective magnetite layer before sustained load. A precipitator downstream of a boiler that skipped dry-out or blowing inherits refractory dust, mill scale and temperature excursions in its first week — the week its baseline is being set.

How long does ESP commissioning take?

Indicatively: cold commissioning of a four-field precipitator takes 5–10 days including air-load curves; hot commissioning and controller/rapping optimisation a further 5–10 days as boiler load allows; the performance guarantee test 2–3 days once the unit is stable at the agreed load window. A combined new-boiler-plus-ESP programme runs 4–8 weeks end to end.

04 — Scope

Scope of the commissioning service

Stated per project; this is the standard split.

SCOPE TABLE — COMMISSIONING SERVICE
Scope itemIncludedExcluded / by others
Pre-energisation mechanical checks (alignment, rapping, hoppers, screens)Included, with recorded protocols per fieldCorrection of major fabrication defects on third-party supply (quoted separately)
Insulator megger, interlock and earthing tests, air-load V-I per fieldIncludedPlant HV switchgear testing upstream of the TR sets
Gas-load V-I, AVC tuning, rapping optimisation, opacity correlationIncludedContinuous emission monitor (CEMS) calibration and certification
Performance guarantee test (EPA M5 / ISO 9096, stated basis)Included — measurement, correction, reportRegulatory witness fees and submission to the authority
Boiler refractory dry-out, safety-valve floating, steam blowing, passivationIncluded on boiler-scope projectsFuel, water, steam and power for commissioning runs; operating crew (plant provides, Arrow directs)
Operator training and documentation handoverIncludedLong-term operation staffing

05 — Method, standards, deliverables

The guarantee test protocol and the handover file

Define the basis first; measure second; argue never.

Why must the test basis be defined before the guarantee test?

Because dust concentration has no meaning without its basis. 40 mg/Nm³ at 6 % O₂ dry and 40 mg/Nm³ at 11 % O₂ are different emissions by a factor of 1.5. The protocol fixes, in writing and in advance: reference O₂, dry basis, boiler load window, fuel condition, soot-blowing state, port locations and traverse plan. Then both parties read one number the same way.

The test itself is an isokinetic traverse to EPA Method 5 or ISO 9096: sampling velocity matched to duct velocity at each traverse point so the probe neither over- nor under-collects coarse particles, with simultaneous O₂, moisture, temperature and velocity measurement for the correction to reference conditions. For biomass and bagasse duty the reference is typically 6 % O₂ dry, consistent with our published design basis (Electrocyclone + four-field ESP: 24 mg/Nm³ @ 6 % O₂ dry — design basis, illustrative calculation, not a guarantee). Guaranteed figures are stated per project after the technical assessment, on the stated basis.

Deliverables at handover:

  • Cold commissioning dossier: alignment records per field, insulator test values, interlock protocols, rapping function reports.
  • Air-load and gas-load V-I curve sets per field — the electrical baseline archive.
  • AVC and rapping settings register with the tuning rationale per field.
  • Opacity–load correlation record.
  • Boiler-side records where in scope: dry-out chart, safety-valve floating certificates, steam-blowing target-plate results, passivation chemistry log.
  • Performance guarantee test report: raw data, corrections, result on the stated basis.
  • Operating and maintenance manual walk-through and operator training record.

The handover file earns its keep for decades. When a field misbehaves in year eight, the maintenance engineer who can lay today's V-I curve over the commissioning curve knows within an hour whether the problem is electrical, mechanical or process-side — and orders the right spare instead of the plausible one. For the same reason we recommend re-recording air-load curves at every major outage: the comparison costs a shift and replaces guesswork with a trend. Plants that lost their original commissioning records can have the baseline reconstructed during a normal shutdown as a stand-alone service.

Commissioning is also where a turnkey emission control project closes out: the same engineers who wrote the design basis run the test that proves it, which removes the most common source of end-of-project dispute — a guarantee written on one basis and tested on another.

FAQ

Engineering questions, answered

What does a healthy air-load V-I curve look like during ESP commissioning?

On ambient air, current stays near zero until corona onset — indicatively 15–25 kV depending on electrode geometry — then rises smoothly and steeply with voltage up to controlled sparkover. Early sparking, a flat current response, or curves differing widely between identical fields point to alignment error, clearance faults or insulator tracking to fix before gas-load.

What is checked in cold commissioning of an electrostatic precipitator?

With the casing open and de-energised: electrode alignment against design clearances, free rapper travel and drop function, hopper heater and level instruments. Closed up: support and shaft insulators meggered — indicatively above 1 GΩ at 5 kV DC — interlocks proven, then air-load V-I curves recorded per field as the electrical baseline for the plant's life.

How is an ESP performance guarantee test carried out?

The basis is defined first: outlet dust in mg/Nm³ at a stated reference O₂, dry, within an agreed boiler load window. Sampling is an isokinetic traverse to EPA Method 5 or ISO 9096, with simultaneous O₂, temperature and flow measurement. Results are corrected to the reference basis; a test without a stated basis proves nothing.

What does boiler-side commissioning include before an ESP sees gas?

Refractory dry-out on a controlled ramp — indicatively 25–50 °C/h with soak holds — safety-valve floating and set-pressure verification, steam-line blowing until target-plate cleanliness criteria are met, and water-chemistry passivation to establish the magnetite layer. Skipping these sends debris, temperature excursions and dirty steam through equipment that was aligned to millimetres.

Why does rapping optimisation happen under gas load, not on air?

Because rapping tuning balances two dust behaviours that only exist with ash on the plates: too-frequent rapping re-entrains collected dust and shows as opacity spikes; too-rare rapping lets the layer grow, insulating the plate and dropping corona current. Timing per field is set against the opacity trace — typically slower in outlet fields where re-entrainment goes straight to the stack.

Send us your plant data

Fuel, boiler capacity, gas flow, current emission and the limit you must meet. An Arrow engineer replies with a technical assessment basis — not a brochure.

Discuss your plant requirement