Boiler · Fabrication scope

Boiler pressure parts — fabrication, repair and replacement

Boiler pressure parts are the components that contain steam and water under pressure: headers, drum repair scope, tube bundles, membrane panels and coils. Arrow Energy Co., Ltd. fabricates them at its Samut Sakhon, Thailand factory to ASME/JIS practice — materials from SA 210 to SA 213 T91 for metal temperatures to about 620 °C, with 100 % material traceability.

SA 210/SA 192 to SA 213 T91, metal temps to ≈ 620 °C
Material range
100 % heat-number transfer, MTC reviewed
Material traceability
1.5 × design pressure per code of construction
Hydrostatic test
705–745 °C soak
PWHT, typical T22 headers

01 — Scope

What we fabricate: headers to coils

Every component that holds boiler pressure, built as a section ready to weld in.

Pressure parts are the boiler's pressure boundary: everything that contains water or steam above atmospheric pressure. Over a boiler's 25–40 year life, most of that boundary is replaced at least once — erosion from abrasive bagasse and rice-husk ash, fireside corrosion, and creep in the hottest sections see to it. Our fabrication scope, part of the wider boiler products line, covers:

  • Headers — superheater, economizer and water-wall headers, drilled, stub-welded and end-capped, in carbon and alloy grades up to SA 335 P22 pipe and equivalent forgings.
  • Drum repair scope — new internals (cyclone separators, chevron driers, feed distribution pipes), nozzle build-up and weld repairs to the shell under the owner's inspection authority. We do not fabricate new drums; drum-shell work is repair and internals only.
  • Tube bundlessuperheater and economizer bundles, bent, welded to headers, and shipped as liftable modules.
  • Membrane panelswater-wall panels, tube-fin-tube welded, delivered flat or pre-formed with openings for burners and soot blowers.
  • Coils — economizer and heat-recovery coils, plain or finned tube.

Each delivery is engineered against the boiler it enters: tube pitch and bend radii from the original arrangement or our own dimensional survey, materials verified rather than assumed, and welds prepared so site tie-in joints land in accessible positions.

02 — Materials

Material grades and their service temperature limits

The grade is set by metal temperature, not steam temperature — and the margin between them is the design.

Which material grade suits which metal temperature?

Carbon steels SA 192 and SA 210 carry water walls and economizers to roughly 425–450 °C metal temperature. Above that, chromium-molybdenum alloys take over: SA 213 T11 to about 540 °C, T22 to about 580 °C, and the 9 % Cr grade T91 to about 620 °C for final superheater sections. Header and pipe equivalents are SA 106 and SA 335 P11/P22.

PRESSURE-PART MATERIALS — INDICATIVE SERVICE LIMITS, DESIGN VALUES PER ASME II-D FOR EACH PROJECT
SpecificationTypeNominal compositionTypical max metal tempTypical service
SA 192Seamless tubeCarbon steel≈ 425 °CWater walls, economizers, low-duty banks
SA 210 A-1/CSeamless tubeCarbon steel≈ 450 °CWater walls, boiler bank, economizers
SA 106 B/CSeamless pipeCarbon steel≈ 425 °CHeaders, downcomers, steam/water piping
SA 213 T11 / SA 335 P11Alloy tube / pipe1¼Cr–½Mo≈ 540 °CPrimary superheaters, hot headers
SA 213 T22 / SA 335 P22Alloy tube / pipe2¼Cr–1Mo≈ 580 °CSecondary superheaters, outlet headers
SA 213 T91Alloy tube9Cr–1Mo–V≈ 620 °CFinal superheater sections, highest duty

Metal temperature runs 20–60 °C above the steam inside it, depending on heat flux and internal scale, and it is metal temperature that drives oxidation and creep. A superheater tube specified at its steam temperature rather than its metal temperature is the single most common original-design error we find — see the re-engineering section below. T91 buys temperature capability but demands discipline in return: preheat, strictly controlled interpass temperature, and post-weld heat treatment in a narrow band, without which the weld zone loses the creep strength the grade was chosen for.

03 — Fabrication

The Samut Sakhon factory: process and traceability

A pressure part is only as good as the paper trail that proves what it is.

Fabrication runs at our factory and R&D centre in Samut Sakhon, Thailand:

  • Tube and pipe bending — mandrel and induction bending with ovality and wall-thinning checks against code limits (wall thinning at the extrados held within the allowance assumed in the thickness calculation).
  • Welding to ASME Section IX — qualified procedures (WPS/PQR) and qualified welders for each material group and process; GTAW roots on all tube butt welds; alloy consumables stored and issued under heated-quiver control.
  • Post-weld heat treatment — furnace and local-resistance PWHT with recorded time–temperature curves; typical soak 705–745 °C for T22/P22 headers, with T91 treated in its tighter code-mandated band.
  • Hydrostatic testing — every pressure part tested at 1.5 × design pressure per the code of construction, held and inspected before draining and drying for shipment.

Traceability is 100 %: every tube, plate and forging enters the works with a mill test certificate (MTC), is checked against the specification — chemistry, mechanicals, heat treatment condition, and the certificate's endorsement (EN 10204 type 3.1, or 3.2 with an independent inspector's counter-signature where the purchaser's specification requires it) — and its heat number is transferred to every cut piece and recorded on the as-built weld map. Positive material identification by XRF backs up the paperwork on alloy grades, because a single T11 stub in a T22 header is invisible to the eye and fails in service. The final dossier — MTCs, WPS/PQR, welder qualifications, NDT reports, PWHT charts, hydrotest certificate, as-built drawings — is what the owner's inspector and insurer actually buy along with the steel.

04 — NDT

Examination methods and extent by class

NDT extent is a decision, made per component class and stated in the ITP.

Four methods cover fabricated pressure parts, each with its own defect target:

  • RT (radiography) — volumetric examination of butt welds; the reference method for tube-to-tube and header butt joints.
  • UT (ultrasonics) — volumetric alternative where geometry or access defeats radiography, and the method for planar defects (lack of fusion) in thicker headers.
  • MT (magnetic particle) — surface and near-surface cracks on ferritic material: nozzle attachment welds, repair excavations, header stub welds.
  • PT (dye penetrant) — surface-breaking defects where MT cannot be applied.

Extent follows component class, agreed in the inspection and test plan (ITP) before the first weld: 100 % RT or UT on critical-class butt welds — superheater outlet headers, main steam piping, drum nozzle repairs — with progressive sampling (typically 10–20 %, escalating on any rejection) on lower-class economizer and water-wall work, and MT/PT on all attachment and repair welds regardless of class. Acceptance is to the code of construction (ASME Section I for boiler proper parts, B31.1 for external piping, or JIS B 8201 where the plant is built to Japanese practice), and examination personnel are qualified to CONFIRM: NDT personnel certification scheme and levels held (e.g. ISO 9712 / ASNT Level II).

05 — Engineering

Replacement in kind, or re-engineering the mistake away

If a section failed early, copying it orders the same failure again.

Should failed superheater sections be replaced with the same material?

Only if the original grade was right for the measured metal temperature. Remaining-life assessments repeatedly find the same pattern: a section specified to the steam temperature, running 30–60 °C hotter in the metal, oxidising and creeping years ahead of schedule. Re-engineering that section — T11 to T22, or T22 to T91 — removes the mechanism; replacement in kind merely restarts the clock on it.

Our engineering step between survey and fabrication therefore asks three questions of every worn section. What was the actual metal temperature — from oxide-scale thickness measurement and hardness survey, not the design sheet? What was the failure mechanism — long-term overheating shows thick-lipped creep fracture and heavy scale; erosion shows polished, thinned flats facing the gas lane; under-deposit corrosion shows pitting at the water side? And does the boiler's current operation match its design — many bagasse units now run harder, with higher final steam temperature, than their 1990s design basis assumed? Where the answers say the original specification was wrong, we propose the upgrade with the arithmetic attached; where they say the wear is simply end-of-life, replacement in kind is the cheaper and correct answer. Erosion-driven cases often justify shields and flow baffles rather than a grade change. The same logic extends to geometry: gas-side lane widths and fin pitch can be corrected at replacement to cut the erosion velocity that killed the original bundle.

06 — Thailand base

A boiler pressure-parts manufacturer in Thailand, supplying for export

Fabrication in Samut Sakhon; deliveries across Southeast Asia, South Asia and the Americas.

Buyers searching for boiler manufacturers in Thailand are usually looking for one of two things: a local fabricator who can hold code practice, or a delivery base closer and faster than Europe or Japan. Arrow Energy Co., Ltd. answers as a Thailand-based pressure-parts fabricator: engineering in Bangkok, fabrication at Samut Sakhon, and export supply supported by Arrow Energy USA LLC for the Americas, the Jakarta office, and representatives in Colombia, the Philippines and India. Work is executed to ASME and JIS practice — Section IX welding qualifications, Section II materials, Section I / B31.1 design and examination rules, or the JIS B 8201 equivalents — with CONFIRM: code stamp scope stated per project. Thai fabrication labour and a domestic tube-and-pipe supply chain price the work competitively against Japanese and European shops, while the documentation dossier travels with the part in a form the receiving country's inspector accepts.

Logistics is engineered with the parts. Bundles and panels are framed and shipped in open-top or flat-rack containers sized to the module split; machined weld preps are capped, alloy components colour-coded and hard-stamped with heat numbers, and tube bores sealed against sea-air moisture with desiccant and end caps — a T91 bore that arrives rusted costs a day of site cleaning per header. Module splits are chosen against the site crane and the boiler-house opening, not against the factory's convenience; for a typical export retrofit the split that saves one site butt weld per tube row repays its shipping volume several times over in outage days. Reference classes for this scope include a 170 t/h bagasse-fired sugar mill in Thailand, a 250 t/h biomass power plant in Thailand and a 230 t/h sugar mill in Colombia — details on the project references page. Fabricated spares for these boilers — loose tubes, bends, stub assemblies — are covered under boiler spares.

FAQ

Engineering questions, answered

What are boiler pressure parts?

Pressure parts are every component containing steam or water under pressure: drums, headers, water-wall membrane panels, superheater and economizer tube bundles, coils, downcomers and interconnecting piping. A 60 t/h biomass boiler contains several hundred tonnes of them, and they are replaced section by section over the boiler's life.

Which material is used for which boiler tube temperature?

Carbon steels SA 192 and SA 210 serve to roughly 425-450 °C metal temperature — water walls and economizers. SA 213 T11 extends to about 540 °C, T22 to about 580 °C, and T91 to about 620 °C for the hottest superheater sections. Pipe and header equivalents are SA 106 and SA 335 P11/P22.

Does Arrow Energy manufacture boiler pressure parts in Thailand?

Yes. Arrow Energy Co., Ltd. fabricates headers, tube bundles, membrane panels and coils at its factory in Samut Sakhon, Thailand, to ASME/JIS practice with welders and procedures qualified to ASME Section IX, and exports to Southeast Asia, South Asia and the Americas. Code-stamp scope is stated per project.

Should worn pressure parts be replaced in kind or upgraded?

Replace in kind only when the original selection was correct. Remaining-life assessments regularly show sections that failed early because the specified grade ran beyond its oxidation limit — for example SA 213 T11 at metal temperatures near 560 °C. There, re-engineering to T22 or T91 removes the failure mechanism instead of rescheduling it.

What NDT is performed on fabricated pressure parts?

Butt welds are examined by radiography or ultrasonics — 100 % on critical headers and steam piping, sampled at 10-20 % on lower-class economizer work, always to a stated acceptance standard. Surface methods, magnetic particle or dye penetrant, cover nozzle attachments and repair excavations. Every part then passes hydrostatic test at 1.5 times design pressure.

Send us your plant data

Fuel, boiler capacity, gas flow, current emission and the limit you must meet. An Arrow engineer replies with a technical assessment basis — not a brochure.

Discuss your plant requirement